Restart of continuous washed coal production

Edenville Energy Plc (AIM: EDL), the AIM quoted company developing the Rukwa coal project in southwest Tanzania (“Rukwa” or the “Project’), is pleased to report that the Company wash plant recommenced continuous operations on 3 March 2020.

As announced on 27 February 2020, a stockpile of approximately 6,000 tonnes of unwashed run of mine (“ROM”) coal, which was mined from the southern pit at Rukwa, has been established adjacent to the wash plant. The wash plant is currently processing ore from that stockpile ahead of the first customer pick-up which is scheduled for 11 March 2020.

As previously announced, the Company expects to commence mining from the northern area at Rukwa during March 2020 as the stockpiles diminish and the ramp up in production continues. As previously noted, the region has so far experienced one of its wettest “rainy” seasons in many years. Should this continue throughout March there is the potential for further disruption to mining operations ahead of the expected end of the rainy season in late April.

For further information please contact:

Edenville Energy Plc

Jeff Malaihollo – Chairman

Alistair Muir – CEO

+44 (0) 20 3934 6630

Strand Hanson Limited

(Financial and Nominated Adviser)

James Harris

Rory Murphy

+44 (0) 20 7409 3494

IFC Advisory Limited

(Financial PR and IR)

Tim Metcalfe

Florence Chandler

+44 (0) 20 3934 6630

Recent Posts

See All

Proposed Share Capital Reorganisation & AGM Notice

Edenville Energy Plc (AIM: EDL), the AIM quoted company operating the Rukwa Coal Project in southwest Tanzania announces that its Annual General Meeting (“AGM”) will be held 10.00 a.m. on 5 January 20

Operational and Corporate Update

Edenville Energy Plc (AIM: EDL), the AIM quoted company operating the Rukwa Coal Project in southwest Tanzania (“Rukwa”) provides an operational and corporate update. Operational Update The Rukwa mine

Interim Results

Edenville Energy plc (AIM: EDL), the company developing a coal project in southwest Tanzania, announces the Company’s unaudited interim results for the six months ended 30 June 2020. Please click here

Comments


bottom of page